This week the Rada will finally consider the government bill on the completion of two units of the Khmelnitsky NPP

It is expected that the completion of the third block will last 2.5-3 years, and the completion of the fourth block will take about another year and a half.

This week the Verkhovna Rada will consider government draft law No. 11146 on the placement, design and construction of power units No. 3 and No. 4 of the Khmelnytsky NPP. This is evidenced by the draft agenda for plenary sessions of parliament.

According to a survey conducted by the sociological group “Rating”, the majority of Ukrainians support the completion of nuclear power units, seeing this as a step towards energy independence and stability.

Power unit No. 3 of the Khmelnitsky NPP is now 75% ready, No. 4 – 25%. It is expected that the completion of the third block will last 2.5-3 years, and the completion of the fourth block will take about another year and a half.

Construction is planned to be financed primarily through loans and…